Services & Costs · Light commercial
Light Commercial Electrical Service, 3-Phase Distribution & Tenant Build-Outs
A scoping guide for owners and managers: choosing service voltage, proving capacity with a 30-day load study, what needs stamped drawings, and what commercial electrical work costs in 2026.

Who this is for
Owners and managers of small and mid-size commercial property: retail and restaurant tenant spaces, offices, light industrial and warehouse units, mixed-use buildings and multifamily common areas — plus businesses adding workplace or fleet EV charging. Projects typically run $5,000 to $50,000+.
- Tenant build-outs and change-of-use fit-outs
- Service upgrades and new three-phase services
- Restaurant kitchen equipment circuits and hood interlocks
- Workplace and fleet Level 2 charging, with load management
- Lighting retrofits and controls for energy code compliance
208Y/120 V or 480Y/277 V?
| 208Y/120 V three-phase | 480Y/277 V three-phase | |
|---|---|---|
| Typical buildings | Retail, restaurants, small offices, multifamily | Warehouses, larger offices, light manufacturing |
| Strengths | Runs 120 V receptacles and most commercial kitchen and HVAC equipment directly | Smaller conductors for large loads; 277 V lighting |
| Trade-off | Larger conductors and gear at high amperage | Needs step-down transformers for 120 V loads |
| EV charging note | Many Level 2 chargers run at 208 V: about 13% less power than at 240 V | Level 2 needs a transformer; DC fast chargers often fed at 480 V |
Sizing an existing service: the 30-day load study
For an existing building, NEC 220.87 (120.87 in NEC 2026) lets the maximum demand be taken from real data instead of a full calculation: 12 months of utility demand records, or a 30-day recorded load study at the service. The highest demand found is multiplied by 125%, and the new load is added. It is often the difference between "you need a new service" and "you have room".
| Method | Data | When to use |
|---|---|---|
| Utility demand history (220.87 / 120.87) | Highest 15-minute demand over 12 months × 125% | Building has demand-metered service |
| Recorded load study | 30 days of continuous metering × 125% | No demand history, or a recent change of use |
| Standard calculation (Article 220 / 120) | Connected loads with demand factors | New service, or major change of use |

Permits, drawings and timing
- Stamped drawings. Many jurisdictions require electrical drawings sealed by a licensed professional engineer above a threshold (often a new service, or loads above a set kVA).
- Utility lead times. New three-phase services and transformer changes run 8–26 weeks depending on the utility and equipment availability.
- Gear lead times. Switchboards and large panelboards can take months; order early.
- Inspections. Rough-in, cover and final, plus fire-alarm and life-safety coordination where applicable.
Typical commercial project ranges
| Project | Typical 2026 range |
|---|---|
| Small tenant fit-out (1,500–3,000 sq ft office or retail) | $5,000 – $25,000 |
| Restaurant fit-out electrical | $20,000 – $50,000+ |
| Service upgrade to 400–800 A three-phase | $15,000 – $50,000+ |
| Workplace Level 2 charging, 4–8 ports with load management | $12,000 – $40,000 |
Scope a commercial project
Tell us the building, service voltage, current amperage and what you are adding. A licensed commercial electrical contractor reviews the scope and quotes.